The Federal Government has commissioned two major electricity infrastructure projects in Gombe State, including a new 2x60MVA transmission substation in Billiri and upgraded transformers at the Gombe Transmission Substation, in a move expected to strengthen power supply across the state and neighbouring communities.

The projects, commissioned on Thursday by the Minister of Power, Joseph Tegbe, comprise a 120MVA transformation facility in Billiri and additional transformer capacity at the Gombe transmission station.

Speaking during the ceremonies, Tegbe said the new infrastructure reflected President Bola Tinubu’s commitment to strengthening the national grid and addressing longstanding electricity supply challenges.
At the Gombe Transmission Substation, the minister disclosed that the installation of a 300MVA, 330/132kV transformer had doubled the station’s upstream transmission capacity from 300MVA to 600MVA, equivalent to 480MW.
He added that the replacement of an existing 30MVA, 132/33kV transformer with a 100MVA unit had increased the station’s downstream transformation capacity to 220MVA, equivalent to 176MW.
According to him, the upgrades would provide additional capacity to serve more electricity consumers, with the improved infrastructure expected to accommodate over 70,000 additional households.
Tegbe said, “The growing electricity demand exceeded the capacity of the existing infrastructure, resulting in suppressed demand. To address this, an additional 300MVA, 330/132kV transformer has been installed, doubling the upstream transmission capacity to 600MVA, equivalent to 480MW.”
He added, “Equally, the existing 30MVA transformer has been replaced with a 100MVA, 132/33kV transformer, increasing the downstream capacity to 220MVA, equivalent to 176MW.”
The minister, who recalled that he had visited Gombe about three to four weeks earlier for the commissioning of a mini-grid in Talasse, Balanga Local Government Area, said the facility had restored electricity to a community that had been without public power supply for 17 years.
He commended the Transmission Company of Nigeria’s management and technical teams, particularly its Managing Director, Engr. Sule Ahmed Abdulaziz, for their efforts in delivering critical transmission projects across the country.
At Billiri, Tegbe described the new substation as a strategic investment capable of supporting agricultural activities, commercial enterprises and economic growth in the area.
The facility, funded by the World Bank and executed by Chris Ejik International Limited, has two 60MVA, 132/33kV transformers, with a combined capacity of 120MVA, equivalent to approximately 96MW, and six outgoing 33kV feeders.
It is connected to the existing Gombe-Savannah-Yola transmission line through a turn-in, turn-out arrangement, providing an additional source of bulk electricity supply to Billiri and neighbouring communities.
Tegbe said, “The commercial exchanges, agricultural activities, small enterprises and growing settlements within this axis require electricity that is both accessible and dependable.
“It is particularly significant that this investment extends our transmission network, ensuring that no community in Nigeria should be denied the opportunity to prosper because the infrastructure required to support its enterprise is unavailable.”
He urged residents of Billiri and neighbouring communities to protect the facilities against vandalism, warning that attacks on public electricity infrastructure would undermine economic activities and disrupt household livelihoods.
The minister also commended the World Bank, TCN, the contractors and other stakeholders for their contributions to the projects.
Earlier, the Managing Director and Chief Executive Officer of TCN, Engr. Sule Ahmed Abdulaziz, said the Billiri substation would strengthen the transmission-distribution interface and provide additional capacity to meet existing and future electricity demand.
He explained that the project would ease pressure on existing infrastructure while giving the Jos Electricity Distribution Company greater flexibility to supply electricity to beneficiary communities.
Abdulaziz said, “The facility is equipped with two 60MVA, 132/33kV power transformers, providing a combined transformation capacity of 120MVA, equivalent to approximately 96MW, with six 33kV outgoing feeders.”
He called on the distribution company to increase its offtake of available electricity to ensure that residents and businesses benefit from the investment.
The TCN boss also urged host communities to safeguard transmission installations, describing them as critical national assets.
At the Gombe Transmission Substation, Abdulaziz disclosed that the reinforcement project was awarded to ISIN Electromechanical Industries Limited in June 2021 and completed in June 2026.
He said the contractor handled the engineering design, manufacture, supply, testing, installation and commissioning of the transformers, alongside the construction of supporting structures and installation of auxiliary equipment.
The TCN managing director noted that replacing transformers at an operational transmission station was technically demanding because electricity supply had to be maintained while the old equipment was removed and the new units installed.
He commended the engineers and contractors for successfully executing the work.
Representing Governor Muhammadu Yahaya, the Commissioner for Energy Resources, Sanusi Ahmad, said the projects would strengthen Gombe’s electricity infrastructure and create opportunities for economic expansion.
He recalled that the state government had earlier commissioned two additional 33kV outgoing feeders in December 2023, describing the latest intervention as another significant investment in the state’s power sector.
Ahmad said the state government was committed to taking advantage of the opportunities created by the Electricity Act 2023 through the implementation of the Gombe State Electricity Law 2025 and the establishment of the Gombe State Electricity Regulatory Commission.
He said, “Our administration will continue to engage relevant Federal Government institutions, electricity market operators, private investors and development partners to explore opportunities that will further strengthen electricity supply across Gombe State.”
The commissioner urged electricity consumers to embrace efficient energy use, promptly report faults and protect public infrastructure, while calling on TCN and distribution companies to sustain the maintenance of their networks.
Also speaking, the Mai Tangle, Danladi Sanusi, commended the Federal Government, the Minister of Power, TCN and the Gombe State Government for the investment.
He described the Billiri substation as more than an electricity project, saying it represented hope, economic empowerment and a brighter future for the people.
“Improved electricity supply will stimulate business, attract investors, create employment opportunities, improve healthcare and education, and accelerate development across Billiri Local Government Area, neighbouring local governments and communities,” he said.
The traditional ruler, however, appealed to the relevant authorities to ensure proper maintenance and effective utilisation of the facilities to guarantee lasting benefits.
The two commissioning ceremonies were attended by government officials, traditional rulers, representatives of the World Bank, contractors, TCN management and other stakeholders.